Rakowski Demolition

Selkirk Mental Health Centre

November 2021

Location: Selkirk, Manitoba

Project Goal:

To complete demolition of building and associated tunnels as well as restoration of the entire site to turn back to green space.

Scope:

Our objective is to provide complete demolition of the entire structure, associated tunnels, and foundations. Our services included in this project were asbestos removal, capping of two tunnels, and constructing infill walls.

Backfilling of the excavation area and complete rehabilitation of the site includes topsoil and sod.

Number of Crew Involved with the Project:

10 men – asbestos approx.
5 men – demolition
2 men  – concrete work

Duration:

Asbestos removal and demolition –  Oct 1, 2021 to Jan 31 , 2022
Infill walls – Jan 15, 2022 to Feb 15, 2022
Backfilling and sod placement – Spring 2022

Rakowski Demolition
Rakowski Demolition
Rakowski Demolition
Rakowski Demolition