September 11, 2017

Souris River Bridge

Conventional Demolition

The demolition and removal of the existing structure over the Souris River on Provincial Road 251, located North of NW 31-01-26W, in the Municipality of Arthur, Bridge Site No. 3246-00. The bridge demolition was completed during the wint...

September 11, 2017

Dominion Malting Plant

Conventional Demolition

Demolishing a 90ft tall kiln building, the concrete structure was situated in the middle of an active plant with access only from one side and surrounded by other buildings. With very little room to work the building was demolished bit...

September 11, 2017

Water Tower Demolition

Conventional Demolition

Standing over 140ft in height the steel water tower was cut into pieces and hoisted down with a crane. With buildings to remain directly under the tower, fire hazard and zero clearance was high priority. Extensive building protection was...