Saskatchewan Bridge Demolition

Saskatchewan Bridge Demolition

March 2022

Location: Borden, Saskatchewan

Project Goal:

The goal for the job was to dismantle and remove old truss sections of the CN Train Bridge and replace it with new ones.

Scope:

PCL Construction lowered truss sections to the ground so our team can cut them apart and get the dismantled material ready for transportation.

Number of Crew Involved with the Project:

6 men

Duration:

21 days, from start to finish.

Borden Saskatchewan Bridge Demolition
Borden Saskatchewan Bridge Demolition
Borden Saskatchewan Bridge Demolition
Borden Saskatchewan Bridge Demolition